Que. Which of the following activities is not one of the four things that need to be accomplished by the generic planning task set?
a. Develop overall project strategy
b. Identify the functionality to deliver in each software increment
c. Create a detailed schedule for the complete software project
d. Devise a means of tracking progress on a regular basis
Answer:Create a detailed schedule for the complete software project