Que. Consider a system having ‘m’ resources of the same type. These resources are shared by three processes P1, P2 and P3 which have peak demands of 2, 5 and 7 resources respectively. For what value of ‘m’ deadlock will not occur?
a. 70
b. 14
c. 13
d. 7
Answer:14
d :(June 23, 2019) a,b,c